Planned
Start |
|
Actual
Start |
|
Event |
|
Comment |
----------- |
|
05/09/12 |
|
Lot Hold |
|
|
----------- |
|
05/10/12 |
|
Contract Signed |
|
|
----------- |
|
05/14/12 |
|
Loan Application |
|
|
----------- |
|
05/23/12 |
|
Loan Approval |
|
|
05/31/12 |
|
05/31/12 |
|
Guardian Appt. |
|
On time |
06/01/12 |
|
06/01/12 |
|
Flooring & Tile Appt. |
|
On time |
06/10/12 |
|
06/10/12 |
|
Selection Lock-in |
|
On time (of course!) |
06/18/12 |
|
06/18/12 |
|
Pre-construction Mtg. |
|
On time |
06/25/12 |
|
06/25/12 |
|
Break Ground |
|
On time |
----------- |
|
06/29/12 |
|
Footings Poured |
|
|
07/02/12 |
|
07/02/12 |
|
Foundation walls poured |
|
On time |
07/03/12 |
|
07/03/12 |
|
Forms stripped |
|
On time |
07/05/12 |
|
07/05/12 |
|
Waterproofing |
|
On time |
07/06/12 |
|
07/06/12 |
|
Back fill |
|
Completed prior to 07/13/12 |
07/09/12 |
|
07/13/12 |
|
Basement slab poured |
|
Delayed by permit |
07/10/12 |
|
07/10/12 |
|
Lumber Delivery |
|
On time |
07/12/12 |
|
07/16/12 |
|
Framing |
|
Further delayed by weather |
07/24/12 |
|
07/30/12 |
|
Trades |
|
Further delayed by weather |
----------- |
|
08/01/12 |
|
Guardian Walkthrough |
|
|
08/07/12 |
|
08/07/12 |
|
Pre-Drywall Meeting |
|
On time |
08/11/12 |
|
08/11/12 |
|
Drywall install |
|
On time |
----------- |
|
08/13/12 |
|
Siding & Shutters |
|
|
08/16/12 |
|
08/16/12 |
|
Mortgage rate lock-in |
|
On time |
----------- |
|
08/16/12 |
|
Stonework |
|
|
08/17/12 |
|
08/14/12? |
|
Finishing & Paint (first coat) |
|
Ahead of schedule |
08/20/12 |
|
08/17/12 |
|
Trim (incl. cabs & doors) |
|
Ahead of schedule |
----------- |
|
08/28/12 |
|
Granite installed |
|
|
08/27/12 |
|
08/29/12 |
|
Tile (showers and floors) |
|
est. per 08/17/12 update |
08/29/12 |
|
08/29/12 |
|
Trades return |
|
est. per 08/13/12 update |
09/04/12 |
|
09/07/12 |
|
Flooring (hardwood, carpet) |
|
originally 08/31/12; new per 08/31/12 update |
09/25/12 |
|
09/25/12 |
|
Final Walkthrough |
|
est. per 08/10/12 update |
09/25/12 |
|
09/25/12 |
|
Inspection |
|
NOT through RH's independent third party |
09/28/12 |
|
09/28/12 |
|
Closing/Settlement |
|
originally 09/17/12; new per 08/24/12 letter |
Could you possibly tell me how you did the progressive photos? I'd like to do it on my blog as well. :)
ReplyDeleteI used PhotoShop CS3 for the animated GIFs (Animation > Make Frames from Layers).
DeleteIf you don't have this Adobe software, there are some other options, including online gifmakers and downloadable software (free or for purchase). I haven't tried these other methods so I don't know how well they work:
* online, just upload your images:
** Picasion GIF maker (http://picasion.com/) - can use photos from Picasa or Flickr
** Gickr.com (http://gickr.com/)
* downloadable SW specific to animated GIF creation:
** UnFREEz (http://www.whitsoftdev.com/unfreez/)
* photo editing software:
** Gimp (http://www.gimp.org/)
** Paint.Net (http://www.getpaint.net/) - this requires a plugin for the animations. Except for the plugin, this is the only one that I have personally downloaded and is a free (decent) alternative to PhotoShop CS or Elements.
Happy editing! :)
Yay! Thank you! :)
DeleteQuestion about your rate lock timing...did you have to relock because your closing was more than 60 days from the day you locked? We can lock now, but it not leaves us about 15 days of cushion and I am concerned that wont be enough.
ReplyDelete